This water treatment plant was constructed for the supply of potable water for the Persian Gulf port city of Bandar Abbas with a flow of 1 cubic meter per second. The plant consisted of two sections: the first section was the clarification process and storage in the city of Minab, while the second section performed the final treatment and storage in the city of Bandar Abbas. The plant was designed by the French Company, Degremont International, who also arranged for the equipment procurement. The entire civil and building works was performed in a subcontract by Tablieh Construction Company.