This run-of-the-river dam is located on the famous Karun
River some 160 km from the provincial capital, Ahwaz. As
one of the cascade dams on Karun, the main objective of
the project is generation of 2000 MW of hydroelectric power,
while the relatively small reservoir is sufficient for the provision
of potable water for the adjacent city of Masjed-e-Soleyman.
Tablieh, as the leading member of the Tablieh–Perlite Joint
Venture was responsible for over 80% of the project civil
works (both above and underground) in the context of various
subcontracts from the Korean-Japanese main contractors,
the Daelim–Sato Joint Venture.
Location |
Khuzestan Province |
Client |
Iran Water & Power Resources Development Co. |
Main contractor |
Daelim-Sato Joint Venture |
Consultant |
Nippon Koei (Japan) -Moshanir-
Lahmeyer International (Germany) |
Scope of work:
Plunge Pool, Tail Pond Dam, Tailrace Tunnel,
Bifurcation & Penstocks, Left Thrust Block
Dam Height |
177 m |
Crest Length |
497 m |
Concrete |
1,100,000 m3 |
Excavation |
21,230,000 m3 |
Embankment |
14,000,000 m3 |
Reinforcement |
45,000 ton |
|
|
|